S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Contingency | 1 | 6100 | 6100 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 1 | 50.2 | 50.2 |
3 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 13.43 | 70.6 | 948.158 |
4 | Filling foundation and around masonry work with moorum I/c ramming layers and watering. | 52.67 | 145.4 | 7658.218 |
5 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 8.85 | 3259.3 | 28844.805 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 8.58 | 2092 | 17949.36 |
7 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2.5:5 (1cement, 2.5 sand, 5metal) | 3.5 | 3259.3 | 11407.55 |
8 | Add for masonry in supper structure above plinth level up to floor two level | 1 | 1 | 1 |
9 | Deduct for kumbhar brick class 20 burnt pajawa in item no. 0603 and 0605 | 1 | 1 | 1 |
10 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:6 (1cement, 6sand) | 1 | 1 | 1 |
11 | Labour only for item no.1604 | 1 | 1 | 1 |