S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Disintegrated or soft rock (not requiring blasting) | 120 | 317.757166666667 | 38130.86 |
2 | (II) Lead upto 150 meters | 13.8 | 73.6050724637681 | 1015.75 |
3 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 18 | 3829.11444444444 | 68924.06 |
4 | (b) Cold twisted / Hot rolled deformed / Thermo mechanicaly treated steel bars | 1106 | 72.2420886075949 | 79899.75 |
5 | Labour only for boulder soling hand packed excluding consolidation. | 552 | 190.534710144928 | 105175.16 |
6 | (c) Hard moorum | 120 | 176.545166666667 | 21185.42 |
7 | Collection of boulders at source (maximum size 0.014cum) without quarrying i.e. picked up boulders. | 553 | 163.567504520796 | 90452.83 |
8 | Stacking of Gravel or Hard Moorum at site without Boxing. | 552 | 22.0707065217391 | 12183.03 |