Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 26-Jun-2024 05:13:24 AM 
Back  
State: MADHYA PRADESH District: KHANDWA Block: BALADI Panchayat: LAHADPUR MAL
Work Code: 1725001027/RC/22012034191142 (PANCH PARMESWAR JAGDISH KE CHAR SE AGANBADI LAHAD)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 26/1/2013 Work start date : 3/7/2013
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 047/1 Sanction Date : 2/7/2013
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
60000 40000 0 0 147000 0 0 187000 0 247000
Financial Sanction Details
Financial\Administrative Sanction No: 02/1 Financial\Administrative Sanction Date 3/7/2013
Fin. Sanc. Amt. (in Rs) NREGA:100000 Panchparmeshwar
147000
Scheme 2
0
Scheme 3
0
Total
247000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Double spade "v" shaped stroke 100mm deep1950.597.5
2Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m000
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)51.143478.5177890.49
4False work for R.C.C. and P.C.C. work in plinth and foundation145.73154.222471.566
5Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)1896.31190.7
6Collection of approved soil having CBR not less than 5, including stacking at quarry.41.771265263.02
7Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 41.776250.62
8Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 51.14321636.48
9Transportation of metal 43.47214.59324.315
10Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 5 Kms. and part there of upto 10 Kms.21.99193.054245.1695
11Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 10 Kms. and part there of upto 30 Kms.11.25193.052171.8125
12Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms.41.77107.644496.1228
13Site clearance, cutting grass, raking into heaps and removing off the premises39.7897.73886.506
14Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed-Hard moorum for Road Work144.0797.714075.639
Total Activity 247000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL4090036000
2CEMENT(BEGS)30030090000
3Centring & Shuttering1407510500
4Display board120002000
5mixer machin (perday)127509000
6murrom41.771506265.5
7PhotoCopy & Stationary1850850
8SAND21.99107523639.25
9transpotation of matel125002500
10Vibrator (Per Day)121001200
11Water With Tenkar76004200
Total Material 187000