The Mahatma Gandhi National Rural Employment Guarantee Act 27-Sep-2024 05:00:31 PM 
Back  
State: MADHYA PRADESH District: KHANDWA Block: BALADI Panchayat: LAHADPUR MAL
Work Code: 1725001027/RC/236 (सीमेन्‍ट का्क्रीट रोड निर्माण रशीद खां समीदखां की )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2011-2012 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 1/10/2011 Work start date : 3/1/2012
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 00528 Sanction Date : 3/1/2012
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
29000 20000 0 0 78000 0 0 98000 0 127000
Financial Sanction Details
Financial\Administrative Sanction No: 0048 Financial\Administrative Sanction Date 19/3/2012
Fin. Sanc. Amt. (in Rs) NREGA:49000 Panchparmeshwar
78000
Scheme 2
0
Scheme 3
0
Total
127000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Dag-beling-Double spade "v" shaped stroke 100mm deep1440.457.6
2Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)28.532608.774426.211
3False work for R.C.C. and P.C.C. work in plinth and foundation198.6128.625539.96
4Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)1905.81102
5Collection of approved soil having CBR not less than 5, including stacking at quarry.30.841183639.12
6Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 30.846185.04
7Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 27.9833.5937.33
8Transportation of metal 30.8483.882586.8592
9Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 5 Kms. and part there of upto 10 Kms.6.28149.76940.4928
10Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 10 Kms. and part there of upto 30 Kms.24.25166.44035.2
11Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 30 Kms. and part there of upto 50 Kms.12.27149.761837.5552
12Site clearance, cutting grass, raking into heaps and removing off the premises41.6281.63396.192
13Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed-Hard moorum for Road Work98.0381.67999.248
Total Activity 127000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL2485020400
2CEMENT(BEGS)17529050750
3Centring & Shuttering100757500
4murrom311504650
5SAND1290010800
6Transportation charges114001400
7Water With Tenkar55002500
Total Material 98000