S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 4175.75 | 4175.75 |
2 | Setting out work Refferance pillers, refferancing bench mark and temporary bench mark Construction of Reference Bench Mark 50x50x70 cm. made of 1:3:6 cement concrete i/c excavation of 50x50x50 cm pit, working benchmark 30x30x45 cm at every 500 m interva | 0.659 | 8673.12 | 5715.58608 |
3 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 3295 | 7.61 | 25074.95 |
4 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 1933.66 | 3.05 | 5897.663 |
5 | Transportation of sand | 1227.72 | 168.54 | 206919.9288 |
6 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 352.97 | 119.29 | 42105.7913 |
7 | Transportation rates for Hume pipes (NP-2) 350 mm to 450 mm dia. | 45 | 106.09 | 4774.05 |
8 | Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-450mm dia | 45 | 1118.02 | 50310.9 |
9 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 705.94 | 20.47 | 14450.5918 |
10 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 1227.72 | 22.58 | 27721.9176 |
11 | Construction of hard shoulder as per clause 407 of specifications for rural roads (MORD), with soil having CBR value not less than 12, inclusive of all leads and lifts, providing 4-5% camber by tractor mounted grader or labourers, watering at OMC and comp | 112.03 | 286.08 | 32049.5424 |
12 | Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clau | 345.98 | 1076.83 | 372561.6434 |
13 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 98.85 | 436.76 | 43173.726 |
14 | Spreading of material mixing by mix in place method by manual means or by tractor mount disk harrows to meet the requirements of Grading and Plasticity given in clause 2.2.2.2,2.2.2.3,2.2.3.1 and 2.2.3.2 of IRC SP: 77-2008 and grading by tractor mount. | 1933.66 | 85.68 | 165675.9888 |