S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 0 | 0 | 0 |
2 | Transportation of metal | 629.06 | 34.29 | 21570.4674 |
3 | Loading of metal in truck, dumper etc. | 629.06 | 42.93 | 27005.5458 |
4 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 629.06 | 44.7 | 28118.982 |
5 | Collection of soft moorum including stacking at quarry. | 629.06 | 122.8 | 77248.568 |
6 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil. | 838.75 | 14 | 11742.5 |
7 | contingency | 1 | 3682 | 3682 |