S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 1 | 1 | 1 |
2 | Transportation of metal | 465 | 99.27 | 46160.55 |
3 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compact | 24.7 | 960 | 23712 |
4 | Lossening of hard soil by ploughing the existing gound | 2.7 | 1535 | 4144.5 |
5 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 50 | 1535 | 76750 |
6 | work charge | 1 | 35832 | 35832 |