Govt. of India
Ministry of Rural Development
Department of Rural Development
The Mahatma Gandhi National Rural Employment Guarantee Act 27-Sep-2024 05:35:16 PM 
Back  
State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: JAWASA
Work Code: 1702001018/RC/510 (1702001018/RC/510)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2012-2013 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : No
Proposal Date : 14/4/2012 Work start date : 11/3/2013
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 457 Sanction Date : 5/1/2013
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
102600 68400 0 0 329000 0 0 398000 0 500000
Financial Sanction Details
Financial\Administrative Sanction No: 210 Financial\Administrative Sanction Date 8/2/2013
Fin. Sanc. Amt. (in Rs) NREGA:171000 Panchparmeshwar
329000
Scheme 2
0
Scheme 3
0
Total
500000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard125002500
2Contingency12141921419
3Dag-beling-Single spade stroke minimum 75mm deep5340.4213.6
4Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete.99.48378.637663.128
5Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)114.312511.5287089.565
6False work for R.C.C. and P.C.C. work in plinth and foundation207.58129.626902.368
7Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)316.845.81837.672
8Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 135233523
9Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 5 Kms. and part there of upto 10 Kms.96.65583.256366.28
10Transportation rates for Masonry stone.14540345403
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work135.0367.89155.034
12Labour difference in case of old SoR179187918
Total Activity 500000
S.NoMaterialQuantityUnit PriceTotal
1Cement263260.168406.3
2Convergence Amount1329000329000
Total Material 398000