S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Loose or soft soil | 225 | 7.00782222222222 | 1576.76 |
2 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 72.72 | 3855.96589658966 | 280405.84 |
3 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 90.144 | 3202.63334220802 | 288698.18 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation. | 285.36 | 174.207527333894 | 49711.86 |
5 | Collection of hard metal other then black trap basalt and granite for building work (without blasting) .
(a) 40 mm nominal size | 75 | 569.3844 | 42703.83 |
6 | b (iii) Dense or hard soil for Tank Work | 5325 | 144.075000938967 | 767199.38 |
7 | (b) Dense or hard soil | 103.872 | 156.78748844732 | 16285.83 |
8 | Citizen Information Board Size 0.9 Meter x 1.2 Meter ( Community Works ) | 1 | 3682 | 3682 |