S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 14.85 | 882 | 13097.7 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:6:12 (1 cement, 6sand, 12metal) | 11.14 | 3307.4 | 36844.436 |
3 | False work for R.C.C. and P.C.C. work in plinth and foundation | 22 | 147.8 | 3251.6 |
4 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 49.5 | 2082.1 | 103063.95 |
5 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Raised and cut pointing | 110 | 127.6 | 14036 |
6 | Demolition above G.L. upto floor two level including disposal of unserviceable materials within 100 metres lead.-Unreinforced cement concrete more then 15 cm thickness. | 32.96 | 650.84 | 21451.6864 |
7 | Lossening of hard soil by ploughing the existing gound | 118.8 | 52.7 | 6260.76 |
8 | contingency | 1 | 18931.8676 | 18931.8676 |