State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: JAURIKOTWAL
Work Code: 1702001083/RC/489 (1702001083/RC/489)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2012-2013 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : No Perspective Plan : Yes
Proposal Date : 14/4/2012 Work start date : 1/3/2013
Present status : No Road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 01/2012-2013 Sanction Date : 22/3/2013
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
79800 53200 0 0 235000 0 0 289000 0 368000
Financial Sanction Details
Financial\Administrative Sanction No: 001/2012 Financial\Administrative Sanction Date 22/3/2013
Fin. Sanc. Amt. (in Rs) NREGA:133000 Panchparmeshwar
235000
Scheme 2
0
Scheme 3
0
Total
368000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard125002500
2Dag-beling-Double spade "v" shaped stroke 100mm deep3900.4156
3Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete.72.67378.627512.862
4Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)83.072511.5208630.305
5False work for R.C.C. and P.C.C. work in plinth and foundation151.71129.619661.616
6Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)231.45.81342.12
7Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 72.674.8348.816
8Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 83.0726.82226.276
9Transportation of 20 MM metal70.61656.646362.526
10Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.12958029580
11Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work98.6767.86689.826
12contingency11655916559
13Labour difference in case of old SoR159415941
Total Activity 368000
S.NoMaterialQuantityUnit PriceTotal
1CEMENT(BEGS)204260.553142
2complite materail punch parmes1235000235000
Total Material 289000