S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 92 | 882 | 81144 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 46 | 3307 | 152122 |
3 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 45 | 3307 | 148815 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 91 | 147 | 13377 |
5 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 243 | 2082 | 505926 |
6 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 432 | 127 | 54864 |
7 | Lossening of hard soil by ploughing the existing gound | 486 | 53 | 25758 |