S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 64.8 | 882 | 57153.6 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 3307.4 | 32.4 | 107159.76 |
3 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 12 mm graded metal is used | 30 | 3307 | 99210 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 64 | 147.8 | 9459.2 |
5 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 172.8 | 2082.1 | 359786.88 |
6 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 384 | 127.4 | 48921.6 |
7 | Lossening of hard soil by ploughing the existing gound | 345.6 | 52.7 | 18213.12 |
8 | contingency | 1 | 2000 | 2000 |