State: MADHYA PRADESH District: BHIND Block: ATER Panchayat: AITHAAR
Work Code: 1702001027/RC/22012034282578 (Gravel road Govt M S to Nahar)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 14/4/2015 Work start date : 3/8/2015
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 33 N Sanction Date : 20/7/2015
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
896000 469000 0 0 0 0 0 469000 0 1365000
Financial Sanction Details
Financial\Administrative Sanction No: 02/33 n Financial\Administrative Sanction Date 24/7/2015
Fin. Sanc. Amt. (in Rs) NREGA:1365000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1365000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard000
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.90004.439600
3Chain and compass survey.-Canals/Roads1628628
4Fly levelling for fixing temporary bench marks.-Above 15 m interval1471471
5Levelling - Headwork.-Below 5 m interval115701570
6Levelling - Headwork.-Above 15 m interval1502.4502.4
7Stacking without boxing.-Puddle earth, moorum, sand or kankar60011.36780
8Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.1450000450000
9Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.60044.126460
10Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN60068.741220
11Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making2394.7530.973997.775
12Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor298735.8106934.6
13Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work5488.487.3479137.32
14Collection of hard moorum including stacking at quarry.600140.784420
15contingency14064740647
16Labour difference in case of old SoR11227012270
Total Activity 1365000
S.NoMaterialQuantityUnit PriceTotal
1Board125002500
2Compaction of Earth Work2394.7530.973997.775
3Compaction of GSB60068.741220
4Compaction of Selected soil298735.8106934.6
5contigency14000040000
6Kilometre Stone (200 M)45002000
7Kilometre Stone (ordinary)220004000
8Transportation charges1198000198000
Total Material 469000