State: MADHYA PRADESH District: KHANDWA Block: PANDHANA Panchayat: DIWAL
Work Code: 1725007024/WC/22012034430902 (पोखर तालाब निर्माण कार्य गौरीशंकर रणजीत के खेत पास)
Work Category: Water Conservation
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2018-2019 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/7/2018 Work start date : 26/12/2018
Present status : Existing Proposed Status : Constr of Water Absorption Trench Trench for Comm
Tech Sanction Details
Technical Sanction No. : 231/diwal Sanction Date : 19/12/2018
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
105000 41000 0 0 0 0 0 41000 0 146000
Financial Sanction Details
Financial\Administrative Sanction No: 27/dewal Financial\Administrative Sanction Date 25/12/2018
Fin. Sanc. Amt. (in Rs) NREGA:146000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
146000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Extra for every additional lift of 1.5 m or part there of-Loose/soft soil and dense/hard soil975.37510.710436.5125
222cm thick dry stone pitching (without quarry spalls) with individual stone of 22cm depth and minimum size 0.01440.5260.410546.2
3Surface dressing two coats with paving bitumen using 18kg. of bitumen 80/100 per 10sqm with 0.15cum of stone chipping 13.2mm nominal size per 10sqm for 1st coat and 11kg. of bitumen 80/100 per 10sqm with 0.10cum of stone chipping 11.2mm nominal size per 119204.29459204.2945
4Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.2197.5950109879.5
5Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Hard moorum2197.592.75933.493
Total Activity 146000
S.NoMaterialQuantityUnit PriceTotal
1Transportation charges of mate20.5200041000
Total Material 41000