S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 5410 | 4.1 | 22181 |
3 | Contingency | 17 | 1000 | 17000 |
4 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Loose or soft soil | 62.1 | 54.1 | 3359.61 |
5 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 850 | 65.7 | 55845 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 2.8 | 2404.1 | 6731.48 |
7 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2.5:5 (1cement, 2.5 sand, 5metal) | 25.5 | 2749.2 | 70104.6 |
8 | Stacking and boxing.-Moorum or sand | 450 | 25.6 | 11520 |
9 | Transportation rates for Masonry stone. | 350 | 138.4 | 48440 |
10 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 450 | 75.78 | 34101 |
11 | Loading of metal in truck, dumper etc. | 527 | 39.42 | 20774.34 |
12 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 850 | 41 | 34850 |
13 | Providing and laying reinforced cement concrete pipes N.P.3 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-1000 mm dia. | 10 | 3555 | 35550 |
14 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 3250 | 22.6 | 73450 |
15 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 3450 | 24 | 82800 |
16 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed- Dense or hard soil for Tank Work | 2920 | 81.2 | 237104 |
17 | Collection of hard moorum including stacking at quarry. | 540 | 130.8 | 70632 |
18 | Collection/Excavation of Gravel Material meeting the requirements of Hard moorum as detailed in RES SOR chapter No. 03 Notes Clause 3.2(C) including stacking and all leads and lifts up to the loading point at quarry. | 540 | 130.8 | 70632 |
19 | Stacking of Gravel or Hard Moorum at site without Boxing. | 1050 | 13.5 | 14175 |
20 | Spreading of material mixing by mix in place method by manual means or by tractor mount disk harrows to meet the requirements of Grading and Plasticity given in clause 2.2.2.2,2.2.2.3,2.2.3.1 and 2.2.3.2 of IRC SP: 77-2008 and grading by tractor mount. | 540 | 80.5 | 43470 |
21 | Rolling & Compaction of granule sub-base of well graded-material Spreading in unformed layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC and compacting with Smooth wheel rollers of 80 to 100 KN static weight to achieve the desired density, complete as pet Technical Specification Clause 401 of Specification for Rural Roads i/c all leads of water etc, complete. | 1 | 5934 | 5934 |
22 | Setting out work (Reference pillars referencing bench mark and temporary bench mark):Painting/Marking of Reference/Working Bench Mark over existing permanent structure Fixing of Reference pegs made of local rough wood for making centre line and toe lines. Fixing of reference poles made of bamboos or jungle wood bellies etc. | 1 | 3276.6 | 3276.6 |