State: MADHYA PRADESH District: GWALIOR Block: BHITARWAR Panchayat: KISHORGARH(P)
Work Code: 1703004013/FP/22012034629229 (फ्लड कंट्रौल वाल निर्माण जसरथ सिंह के खेत के पास टेकपुर)
Work Category: Other Works
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2022-2023 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : NO Perspective Plan : NO
Proposal Date : 17/4/2022 Work start date : 22/5/2022
Present status : Weak Embankment Proposed Status : Constr of Flood/ Diversion Channel for Community
Tech Sanction Details
Technical Sanction No. : TS- 131/013 Sanction Date : 20/5/2022
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost 15th Finance Commission scheme2 scheme3 Total
524600 349700 0 0 115000 0 0 465000 0 989300
Financial Sanction Details
Financial\Administrative Sanction No: AS- 11/013 Financial\Administrative Sanction Date 21/5/2022
Fin. Sanc. Amt. (in Rs) NREGA:874300 15th Finance Commission
115000
Scheme 2
0
Scheme 3
0
Total
990000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.1837.041288.32
2Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil164.7156.7925823.313
3Dag-beling-Single spade stroke minimum 75mm deep610.530.5
4Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m686.25114.5678616.8
5Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering.32.943202.91105503.8554
6Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)15.863947.4562606.557
7False work for R.C.C. and P.C.C. work in plinth and foundation3.05174.2531.31
8Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:4 (1cement, 4sand)204.962732.88560131.0848
9Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing48.8171.358361.88
10Stacking without boxing.-Masonry stones, pitching stones or boulders204.9646.689567.5328
11Transportation of metal 46.897234.0410975.77388
12Transportation rates for Masonry stone.204.96506.24103758.9504
13Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.97.481226.3822067.74878
Total Activity 990000
S.NoMaterialQuantityUnit PriceTotal
120 MM METAL13.5150020250
240 mm size HG metal28.83255.387362.6054
3Cement540370199800
4Contengency11007310073
5Sand1101170128700
6Transportation charges204.96480.6598514.024
Total Material 465000