S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 612.5 | 6.64524081632653 | 4070.21 |
2 | Providing stone chips under stone pitching | 75 | 454.8792 | 34115.94 |
3 | (a) Other then black trap Basalt or granite | 43.25 | 301.756994219653 | 13050.99 |
4 | (XI) 6 Km. Lead | 43.25 | 262.241387283237 | 11341.94 |
5 | (XIV) 9 Km. Lead | 455 | 200.12167032967 | 91055.36 |
6 | (XX) 20 Km. Lead | 245 | 289.369918367347 | 70895.63 |
7 | (III) 1.5 Km. Lead | 111.38 | 104.676602621656 | 11658.88 |
8 | (a) Boulders | 65 | 576.088153846154 | 37445.73 |
9 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 111.38 | 428.449991021727 | 47720.76 |
10 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 811.38 | 21.7849466341295 | 17675.87 |
11 | a (iii) Loose or soft soil for Tank Work | 46.31 | 100.964802418484 | 4675.68 |
12 | b (iii) Dense or hard soil for Tank Work | 245 | 136.306244897959 | 33395.03 |
13 | c (iii) Hard moorum for Tank Work | 506.48 | 181.559943136945 | 91956.48 |
14 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 53.06 | 577.365435356201 | 30635.01 |