S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 2207.4 | 7.02398296638579 | 15504.74 |
2 | Disintegrated or soft rock (not requiring blasting) | 115.4 | 335.867677642981 | 38759.13 |
3 | Single spade stroke minimum 75mm deep | 2207.4 | 0.404561928060161 | 893.03 |
4 | (I) 1.50 m. to 3.00 m. | 697.76 | 10.4835616831002 | 7315.01 |
5 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 80.87 | 3202.63336218622 | 258996.96 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 20mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work ( if 20 mm metal is used in place of 40mm metal in item number 04.13 & 04.15)
(a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 83.62 | 3947.45144702224 | 330085.89 |
7 | False work for R.C.C. and P.C.C. work in plinth and foundation. | 83.73 | 174.207571957482 | 14586.4 |
8 | 22cm thick dry stone picked up boulder pitching i/c picking of boulder with individual size of 22cm depth. | 455.87 | 215.94301006866 | 98441.94 |
9 | Add extra item no. 1274 for quarried boulder pitching. | 455.87 | 183.568495404392 | 83683.37 |
10 | (c) Construction of masonry or concrete(rate for 1Cum. of masonry or concrete) | 558.8 | 13.8847530422334 | 7758.8 |
11 | (XXVI) 35 Km. Lead | 143.86 | 455.325941887947 | 65503.19 |
12 | (XV) 10 Km. Lead | 100.29 | 273.323561671154 | 27411.62 |
13 | (XXII) 24 Km. Lead | 71.51 | 325.465808977765 | 23274.06 |
14 | (IV) 2.0 Km. Lead | 394.31 | 113.817681519617 | 44879.45 |
15 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 394.31 | 452.889782151099 | 178578.97 |
16 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 2093.28 | 21.9341655201406 | 45914.35 |
17 | Benching the seat of embankment to an average depth of 15cm and cross slope of 1 in 12 including cleaning of all foreign material, vegetation and other growth like grass and plant roots and removing the rubbish up to a suitable distance and dressing etc. complete. | 154.13 | 172.890027898527 | 26647.54 |
18 | (b) Dense or hard soil | 461.6 | 156.787456672444 | 72373.09 |
19 | Loosing of hard soIl such as moorum etc. By ploughing (tractor ect.) the existing ground exceeding 30cm in depth as well as 10 sqm on plan including all running expanses of machine. | 7475.99 | 3.60018004304447 | 26914.91 |
20 | Spreading dressing, breaking of clods of ploughed earth upto 20m lead and lift upto 1.5m disposed soil to be leveled and neatly dressed. | 7475.99 | 79.0971750898543 | 591329.69 |