S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 1200 | 6.64524166666667 | 7974.29 |
2 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 18.8 | 3823.5414893617 | 71882.58 |
3 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 170.76 | 3170.20912391661 | 541344.91 |
4 | Plum cement concrete 1:2:4 with 75% graded metal of 40mm size and 25% plums of 150mm size. | 10 | 2556.184 | 25561.84 |
5 | Centering and shuttering including strutting , propping etc. and removal of form work for P.C.C. work in foundation, footing, bases for column | 154.8 | 161.093281653747 | 24937.24 |
6 | (XVIII) 16 Km. Lead | 167.95 | 286.528550163739 | 48122.47 |
7 | (XVII) 14 Km. Lead | 111.46 | 242.128566301812 | 26987.65 |
8 | c (iii) Hard moorum for Tank Work | 138.32 | 181.559933487565 | 25113.37 |
9 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 64.32 | 577.419776119403 | 37139.64 |