S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 1870.9 | 7.02 | 13133.718 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 4.92 | 3426.49 | 16858.3308 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2.5:5 (1cement, 2.5 sand, 5metal) | 47.79 | 3830.98 | 183082.5342 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 136.48 | 187.8 | 25630.944 |
5 | 22cm thick dry stone pitching (without quarry spalls) with individual stone of 22cm depth and minimum size 0.014 | 308.15 | 608.1 | 187386.015 |
6 | Providing stone chips under stone pitching | 525.42 | 608.1 | 319507.902 |
7 | Transportation of metal | 115.59 | 137.73 | 15920.2107 |
8 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 146.67 | 243.71 | 35744.9457 |
9 | Rolling and consolidating water bound mecadam coat with any size of metal of any thickness upto 100mm thickness(including rolling screening or binding materials) including watering & filling in depressions which occur during the process with power roller-Including hire and running expenses of roller | 3355.06 | 22.93 | 76931.5258 |
10 | FOR EARTHEN DAM - Benching the seat of embankment over to an average depth of 15cm and cross slope of 1:12 including earth work removing the rubbish upto a distance of 50m including dressing. | 389.51 | 172.89 | 67342.3839 |
11 | FOR EARTHEN DAM - Puddle filling of good clay including lead upto 50m including mixing watering and kneeding by tamping ramming and laying etc. | 243.71 | 452.46 | 110269.0266 |
12 | FOR EARTHEN DAM - Providing fitter blanket, horizontally, including laying, Spreading, packing etc. in layers of required thickness but excluding excavation of foundation.-Metal 80 mm nominal size | 139.16 | 888 | 123574.08 |
13 | FOR EARTHEN DAM - Construction of rock toe in earthen embankments including laying and hand packing, dressing, wedging and finishing over surface with.-Boulders | 62.73 | 897.52 | 56301.4296 |
14 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. | 3355.06 | 79.09 | 265351.6954 |
15 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard moorum for Tank Work | 60.47 | 191.91 | 11604.7977 |
16 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Disintegrated or soft rock (not requiring blasting) for Tank Work | 472.89 | 611.77 | 289299.9153 |
17 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.Hard rock requiring blasting for Tank Work | 288.77 | 645.19 | 186311.5163 |
18 | Lossening of hard soil by ploughing the existing gound | 3355.06 | 3.05 | 10232.933 |
19 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 3355.06 | 79.09 | 265351.6954 |
20 | work charge | 1 | 74000 | 74000 |