State: MADHYA PRADESH District: DHAR Block: MANAWAR Panchayat: Rajukhedi
Work Code: 1722011002/RC/22012034525624 (Sudur Sampark Sadak Sala Patelpura Main Road Se Mujaldapura, Sala, Rajukhedi )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2020-2021 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 14/4/2020 Work start date : 13/6/2020
Present status : Earthern road Proposed Status : Construction of Gravel Road Roads for Community
Tech Sanction Details
Technical Sanction No. : 1722011/2020-2021/224392/TS Sanction Date : 21/6/2020
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
819185.25 655148.48 1055.08 16022.62 0 0 0 673000 0 1491411.43
Financial Sanction Details
Financial\Administrative Sanction No: 1722011/2020-2021/224392/AS Financial\Administrative Sanction Date 21/6/2020
Fin. Sanc. Amt. (in Rs) NREGA:1491410 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1492000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.48006.5419479166666731401.35
2(a) C.C. 1:2:4 (1cement, 2sand, 4metal)37.023812.18611561318141127.13
3(b) C.C. 1:3:6 (1cement, 3sand, 6metal)18.233158.5019199122357579.49
4False work for R.C.C. and P.C.C. work in plinth and foundation.121.5164.45193415637919980.91
5(V) 2.5 Km. Lead732.63118.2748590693886651.71
6(VII) 3.5 Km. Lead1470132.14525170068194253.52
7(VIII) 4.0 Km. Lead450138.93035555555662518.66
8(b) Selected granular material in filling. cum 584.616.54624.24365175332510324.99
9(c) 600mm dia15882.56213238.43
10(b) 1000 mm dia.123758.647545103.77
11Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making 4% camber and required Grade by tractor mounted grader or labourers, watering at OMC and compacted by 80 to 100 kN static weight rollers to achieve desired density minimum 97% as per table 300.1 and 300.2 of (MORD) - i/c required leads and lifts of materials etc. complete.975.6317.345048840236616922.35
12Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor mounted grader or labourers, watering at OMC and compacted by 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7). Complet compaction work as per specifications for rural roads (MORD) clause 303, i/c required leads and lifts of materials etc. complete.147019.112571428571428095.48
13Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compacted by 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7). Complete compaction work as per specifications for rural roads (MORD) clause 303, i/c required leads and lifts of materials etc. complete.60023.932583333333314359.55
14b (i) Dense or hard soil for Road Work975.63134.186812623638130916.68
15Collection of approved soil having CBR not less then 5, including stacking at quarry.1470181.206802721088266374
16Collection/Excavation of Graval Material meeting the requirements of Hard Moorum as detailed in RES SOR chaper 03 Notes Clause 3.2© including stacking and all leads and lifts up to loading point at quarry.450208.25993716.55
17Spreading of material, mixing by mix in place method by manual means or by Tractor mount disk herrows to meet the requirements of Grading and Plasticity given in clause 2.2.2.2, 2.2.2.3, 2.2.3.1 and 2.2.3.2 of IRC:SP:77-2008. and grading by tractor mount grader to get the required profile.1920129.605578125248842.71
Total Activity 1462000
S.NoMaterialQuantityUnit PriceTotal
10002-Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper5.5248854888.74
20038-Tractor with ripper attachment4.172521248862.39
30055-Smooth Wheeled Roller 8 to 10 tonne41.79632369863.9268
40057-Water Tanker 5 to 6 KL Capacity60.91251187187.675
50084-Hire charges of Diesel truck - 9 tonne (without POL)82.00272242183850.0534
60297-Stone Aggregate(single size): 10 mm nominal size4.07176302565.171
70367-Portland Cement16.3415551190058.0065
80763-Glue 1.987.9515.741
90765-Hessian cloth1.58.913.35
100983-Fine sand (zone IV)25.40551076.2527342.669375
1110-Miscellaneous /Contingencies charges12500025000
121235-Diesel oil730.1146849647.752
131706-R.C.C. pipes NP2 class 600 mm dia61622.59735
141720-R.C.C. collars NP2 class 600 mm dia4.5141.6637.2
153-Display Board150005000
165001-Mobil oil26.0113182.94757.46677
17MR6001-Stone Aggregate(single size): 40 mm nominal size other than BT31.094152516324.4025
18MR6039-Water3654750.0518273.75
19MR6045-RCC NP-3 pipe 1000mm(based on LUN rate)122977.7835733.36
20MR6046-RCC NP-3 collar 1000mm(based on LUN rate)3.6266.67960.012
21MR6055-Well Graded granular material19.8444246.194885.492836
22MR6082-Stone Aggregate (Metal) 20mm nominal size (BT Metal) (Rate at quarry)12.51736828536.7986
23MR6091-WOOD-Kail wood 2nd class0.455615825.67210.14336
Total Material 522000