State: MADHYA PRADESH District: GWALIOR Block: BHITARWAR Panchayat: SHYAMPUR(P)
Work Code: 1703004074/RC/22012034210925 (मुरमीकरण मैन रोड से मनोज सिंह के खेत तक )
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 26/1/2014 Work start date : 25/2/2014
Present status : Earthern road Proposed Status : Sand Moram
Tech Sanction Details
Technical Sanction No. : 3043 Sanction Date : 19/2/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
179260 115533 0 0 0 0 0 116000 0 294793
Financial Sanction Details
Financial\Administrative Sanction No: 74/214 Financial\Administrative Sanction Date 20/2/2014
Fin. Sanc. Amt. (in Rs) NREGA:294793 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
295000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Contingency123207.6323207.63
2Dag-beling-Single spade stroke minimum 75mm deep2000.240
3Collection of approved soil having CBR not less then 12, including stacking at quarry.621105.365391.3
4Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.621191.16118710.36
5Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN62169.743283.7
6Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Dense or hard soil.345012.844160
Total Activity 295000
S.NoMaterialQuantityUnit PriceTotal
1Compaction of Earth Work62128.717822.7
2contangency and work charges13485.873485.87
3Transpotation of Mooram621151.7394224.33
Total Material 116000