S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 400 | 2.81 | 1124 |
2 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 60 | 144.07 | 8644.2 |
3 | Dag-beling-Single spade stroke minimum 75mm deep | 300 | 0.4 | 120 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 30 | 3202.63 | 96078.9 |
5 | False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift | 51.5 | 174.2 | 8971.3 |
6 | Repairs to plaster in patches of 2.50 sqm and under and 10 to 15mm thick including cutting the patch in proper shape and replastering the surfaces of the walls including disposal of rubbish to the Camping ground within a lead of 50 metres with.-Lime mortar 1:2 (1Lime, 2Sand) | 45 | 3947.45 | 177635.25 |
7 | Construction of granular sub-base (GSB) by naturally occurred material or river born material or by crushed metal or mixture of two or more, to bring the material in appropriate grading mentioned in table 400.1, (I, II or III) of specifications for rural | 105 | 400.9 | 42094.5 |