S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 0 | 0 | 0 |
2 | Dag-beling-Single spade stroke minimum 75mm deep | 200 | 0.3 | 60 |
3 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 11.25 | 882 | 9922.5 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 9 | 3307.4 | 29766.6 |
5 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 100 | 59.1 | 5910 |
6 | Pointing on CR masonry with cement mortar 1:4(1cement, 4sand)-Flush pointing | 360 | 81.3 | 29268 |
7 | Demolition above G.L. upto floor two level including disposal of unserviceable materials within 100 metres lead.-Lime concrete. | 104.25 | 1079 | 112485.75 |
8 | Transportation of metal | 18.9 | 323.7 | 6117.93 |
9 | Transportation rates for Masonry stone. | 104.25 | 394.38 | 41114.115 |
10 | Transportation rates for Lime (fat), Hydraulic or any other. | 51.46 | 135.48 | 6971.8008 |
11 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Loose or soft soil | 56.25 | 96.2 | 5411.25 |