S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | (III) Lead upto 200 meters | 420 | 126.363380952381 | 53072.62 |
2 | (I) 1.50 m. to 3.00 m. | 2111.25 | 11.3571912374186 | 23977.87 |
3 | (II) 3.00 m to 4.50 m | 982.5 | 19.8900050890585 | 19541.93 |
4 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 8.4 | 3467.98809523809 | 29131.1 |
5 | (e) In Cement mortar 1:6 (1cement, 6sand) | 22.05 | 3022.09387755102 | 66637.17 |
6 | (XXIX) 50 Km. Lead | 194.85 | 937.692891968181 | 182709.46 |
7 | Benching the seat of embankment to an average depth of 15cm and cross slope of 1 in 12 including cleaning of all foreign material, vegetation and other growth like grass and plant roots and removing the rubbish up to a suitable distance and dressing etc. complete. | 450 | 187.297511111111 | 84283.88 |
8 | Site clearance, cutting grass, raking into heaps and removing off the premises | 3000 | 3.05382333333333 | 9161.47 |
9 | a (i) Loose or soft soil for Road Work | 6273.75 | 115.624989838613 | 725402.28 |
10 | (b) Dense or hard soil | 25.2 | 169.853174603175 | 4280.3 |
11 | 22cm thick dry stone pitching ( without quarry spalls ) with individual stone of 22 cm depth and minimum size 0.014 cum | 576 | 444.225607638889 | 255873.95 |