S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Disintegrated or soft rock (not requiring blasting) | 51.476 | 363.85655451084 | 18729.88 |
2 | (a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 250.446 | 4237.92490197488 | 1061371.34 |
3 | (b) C.C. 1:3:6 (1cement, 3sand, 6metal) | 52.683 | 3467.98853520111 | 182704.04 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 20mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work ( if 20 mm metal is used in place of 40mm metal in item number 04.13 & 04.15)
(a) C.C. 1:2:4 (1cement, 2sand, 4metal) | 17.094 | 4408.24558324558 | 75354.55 |
5 | Extra rate for laying cement concrete in or under water or liquid mud including cost of pumping and bailing out and removing slush etc. complete. | 21.549 | 94.4596036939069 | 2035.51 |
6 | False work for R.C.C. and P.C.C. work in plinth and foundation. | 397.9 | 191.19934656949 | 76078.22 |
7 | (b) Dense or hard soil | 77.216 | 169.853139245752 | 13115.38 |
8 | (c) Hard moorum | 128.692 | 202.158020700587 | 26016.12 |