S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 0 | 0 | 0 |
2 | Site clearance, cutting grass, raking into heaps and removing off the premises | 540 | 1.8 | 972 |
3 | Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Dense or hard soil | 232.875 | 96.4 | 22449.15 |
4 | contingency | 849 | 1 | 849 |
5 | Labour difference in case of old SoR | 149 | 2 | 298 |