S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2500 | 2500 |
2 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 6300 | 4.1 | 25830 |
3 | Chain and compass survey.-Canals/Roads | 0.7 | 584 | 408.8 |
4 | Fly levelling for fixing temporary bench marks.-Above 15 m interval | 0.7 | 438 | 306.6 |
5 | Levelling - Headwork.-Below 5 m interval | 0.7 | 1460 | 1022 |
6 | Levelling - Headwork.-Above 15 m interval | 0.7 | 467 | 326.9 |
7 | Stacking and boxing.-Moorum or sand | 420 | 15 | 6300 |
8 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1 | 218000 | 218000 |
9 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 420 | 41 | 17220 |
10 | Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN | 420 | 59.7 | 25074 |
11 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1676.325 | 20.7 | 34699.9275 |
12 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2090.9 | 22.1 | 46208.89 |
13 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 3841 | 81.2 | 311889.2 |
14 | Collection of hard moorum including stacking at quarry. | 420 | 130.8 | 54936 |
15 | contingency | 1 | 41220 | 41220 |
16 | Labour difference in case of old SoR | 1 | 38800 | 38800 |