S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Site clearance, cutting grass, raking into heaps and removing off the premises | 0 | 0 | 0 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 220 | 191.79 | 42193.8 |
3 | Providing and laying in foundation, plinth and under floors lime concrete with 40mm nominal size graded stone aggregates (metal) and 40% lime mortar. i/c ramming in layers and curing complete excluding cost of form work.-Lime mortar 1:2 (1lime putty, 2sand) | 20.93 | 3202.63 | 67031.0459 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2.5:5 (1cement, 2.5 sand, 5metal) | 0 | 6243.26 | 0 |
5 | False work for R.C.C. and P.C.C. work in plinth and foundation | 0 | 174.2 | 0 |
6 | Steel work in single section including in cutting, hoisting fixing in position in R.S. joists, channels, angles, tee. | 1911 | 0 | 0 |
7 | Coal tarring 2 coats on new wood and wood based surface . | 1 | 3645 | 3645 |
8 | Transportation of metal | 60.5 | 0 | 0 |
9 | Transportation of sand | 14 | 293.59 | 4110.26 |
10 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 30.5 | 213.9 | 6523.95 |