State: MADHYA PRADESH District: DAMOH Block: BATIYAGARH Panchayat: MAGRON
Work Code: 1711003013/IF/410 (कपिल धारा कूप निर्माण कार्य हमीद खां/गनीम खां)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2011-2012 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 1/11/2011 Work start date : 27/12/2011
Present status : Not Exist Proposed Status : Well
Tech Sanction Details
Technical Sanction No. : 1438 Sanction Date : 26/12/2011
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
207758 136242 0 0 0 0 0 137000 0 344000
Financial Sanction Details
Financial\Administrative Sanction No: 04/J Financial\Administrative Sanction Date 27/12/2011
Fin. Sanc. Amt. (in Rs) NREGA:344000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
344000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard120002000
2Contingency11704417044
3Work charge810008000
4Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead357.7521.97834.725
5Labour only for item no.0402200.4535.87176.11
6Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete.000
7Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)0.693089.92132.031
8Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used0.69169.4116.886
9Random/ uncoursed rubble masonry in plinth and foundation, stones laid dry, well bounded, faced with selected stones and built with through stones evenly placed at the rate of two per sqm122.08814.699446.368
10Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:6 (1cement, 6sand)4.481984.78891.456
11Add extra for brick masonry circular in plan, I/c wells to a mean radius not exceeding 6m (Such as well stening and other similar type of works)127.62265.533883.11
12Add to item no.0605 and 0609 for well staining-For every 3meter up to 15 meter depth.122.08172.321034.384
13TRANSPORTATION OF MATERIAL13181231812
14Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing25.6271.21824.144
15Collection of hard metal other then black trap basalt and granite for building work (without blasting) .-40 mm nominal size8.1330.82679.48
16Transportation of metal 24.3153.83737.34
17Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil86.7882.87185.384
18Earth work for well excavation-Soil lift from 3.50 m. to 4.00 m.22.19140.63119.914
19Earth work for well excavation-Soil lift from 5.00 m. to 5.50 m.20.03160.43212.812
20Earth work for well excavation-Soil lift from 10.50 m. to 11.00 m.14.03256.23594.486
21Earth work for well excavation-soil lift from 14.00 m. to 14.50 m.12.04332.54003.3
22Earth work for well excavation-Hard moorum lift from 1.5 m. to 2.00 m.26.03114.22972.626
23Earth work for well excavation-Hard moorum lift from 2.00 m. to 2.50 m.24.96120.83015.168
24Earth work for well excavation-Hard moorum lift from 2.50 m. to 3.00 m.23.69127.43018.106
25Earth work for well excavation-Hard moorum lift from 3.00 m. to 3.50 m.22.941343073.96
26Earth work for well excavation-Hard moorum lift from 5.50 m. to 6.00 m.19.341673229.78
27Earth work for well excavation-Hard moorum lift from 4.00 m. to 4.50 m.21.46147.23158.912
28Earth work for well excavation-Hard moorum lift from 4.50 m. to 5.00 m.20.74153.83189.812
29Earth work for well excavation-Hard moorum lift from 6.00 m. to 6.50 m.18.65175.73276.805
30Earth work for well excavation-Hard moorum lift from 6.50 m. to 7.00 m.17.98184.43315.512
31Earth work for well excavation-Hard moorum lift from 7.00 m. to 7.50 m.17.33193.13346.423
32Earth work for well excavation-Hard moorum lift from 7.50 m. to 8.00 m.16.68201.83366.024
33Earth work for well excavation-Hard moorum lift from 8.00 m. to 8.50 m.16.05210.53378.525
34Earth work for well excavation-Hard moorum lift from 8.50 m. to 9.00 m.15.43219.23382.256
35Earth work for well excavation-Hard moorum lift from 9.00 m. to 9.50 m.14.96227.93409.384
36Earth work for well excavation-Hard moorum lift from 9.50 m. to 10.00 m.14.62236.63459.092
37Earth work for well excavation-Hard moorum lift from 10.00 m. to 10.50 m.14.31245.33510.243
38Earth work for well excavation-Hard moorum lift from 11.00 m. to 11.50 m.13.75267.13672.625
39Earth work for well excavation-Hard moorum lift from 11.50 m. to 12.00 m.13.452783739.1
40Earth work for well excavation-Hard moorum lift from 12.00 m. to 12.50 m.13.15288.93799.035
41Earth work for well excavation-Hard moorum lift from 13.00 m. to 13.50 m.12.61310.73917.927
42Earth work for well excavation-Hard moorum lift from 13.50 m. to 14.00 m.12.33321.63965.328
43Earth work for well excavation-Hard moorum lift from 14.50 m. to 15.00 m.11.78343.44045.252
Total Activity 344000
S.NoMaterialQuantityUnit PriceTotal
120 M.M. METAL0.481000480
240 M.M. METAL132.468.11072.926
3boldar137.510.81485
4Cement(bori)122503000
5Contagecny196429642
6dewatering510005000
7Display board120002000
8MASON (PERDAY)7930023700
9P V C PIPE 2100
10Sand2.187871715.66
11SEND MOTARS215.665.41164.564
12Stone other than Granite130.4547561963.75
13Transpotation Charges12500025000
14VAT 13000
Total Material 137000