S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Contingency | 1 | 17044 | 17044 |
3 | Work charge | 8 | 1000 | 8000 |
4 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 357.75 | 21.9 | 7834.725 |
5 | Labour only for item no.0402 | 200.45 | 35.8 | 7176.11 |
6 | Filling in plinth with sand under floors including watering, ramming, consolidating and dressing complete. | 0 | 0 | 0 |
7 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 0.69 | 3089.9 | 2132.031 |
8 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 0.69 | 169.4 | 116.886 |
9 | Random/ uncoursed rubble masonry in plinth and foundation, stones laid dry, well bounded, faced with selected stones and built with through stones evenly placed at the rate of two per sqm | 122.08 | 814.6 | 99446.368 |
10 | Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:6 (1cement, 6sand) | 4.48 | 1984.7 | 8891.456 |
11 | Add extra for brick masonry circular in plan, I/c wells to a mean radius not exceeding 6m (Such as well stening and other similar type of works) | 127.62 | 265.5 | 33883.11 |
12 | Add to item no.0605 and 0609 for well staining-For every 3meter up to 15 meter depth. | 122.08 | 172.3 | 21034.384 |
13 | TRANSPORTATION OF MATERIAL | 1 | 31812 | 31812 |
14 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 25.62 | 71.2 | 1824.144 |
15 | Collection of hard metal other then black trap basalt and granite for building work (without blasting) .-40 mm nominal size | 8.1 | 330.8 | 2679.48 |
16 | Transportation of metal | 24.3 | 153.8 | 3737.34 |
17 | Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 86.78 | 82.8 | 7185.384 |
18 | Earth work for well excavation-Soil lift from 3.50 m. to 4.00 m. | 22.19 | 140.6 | 3119.914 |
19 | Earth work for well excavation-Soil lift from 5.00 m. to 5.50 m. | 20.03 | 160.4 | 3212.812 |
20 | Earth work for well excavation-Soil lift from 10.50 m. to 11.00 m. | 14.03 | 256.2 | 3594.486 |
21 | Earth work for well excavation-soil lift from 14.00 m. to 14.50 m. | 12.04 | 332.5 | 4003.3 |
22 | Earth work for well excavation-Hard moorum lift from 1.5 m. to 2.00 m. | 26.03 | 114.2 | 2972.626 |
23 | Earth work for well excavation-Hard moorum lift from 2.00 m. to 2.50 m. | 24.96 | 120.8 | 3015.168 |
24 | Earth work for well excavation-Hard moorum lift from 2.50 m. to 3.00 m. | 23.69 | 127.4 | 3018.106 |
25 | Earth work for well excavation-Hard moorum lift from 3.00 m. to 3.50 m. | 22.94 | 134 | 3073.96 |
26 | Earth work for well excavation-Hard moorum lift from 5.50 m. to 6.00 m. | 19.34 | 167 | 3229.78 |
27 | Earth work for well excavation-Hard moorum lift from 4.00 m. to 4.50 m. | 21.46 | 147.2 | 3158.912 |
28 | Earth work for well excavation-Hard moorum lift from 4.50 m. to 5.00 m. | 20.74 | 153.8 | 3189.812 |
29 | Earth work for well excavation-Hard moorum lift from 6.00 m. to 6.50 m. | 18.65 | 175.7 | 3276.805 |
30 | Earth work for well excavation-Hard moorum lift from 6.50 m. to 7.00 m. | 17.98 | 184.4 | 3315.512 |
31 | Earth work for well excavation-Hard moorum lift from 7.00 m. to 7.50 m. | 17.33 | 193.1 | 3346.423 |
32 | Earth work for well excavation-Hard moorum lift from 7.50 m. to 8.00 m. | 16.68 | 201.8 | 3366.024 |
33 | Earth work for well excavation-Hard moorum lift from 8.00 m. to 8.50 m. | 16.05 | 210.5 | 3378.525 |
34 | Earth work for well excavation-Hard moorum lift from 8.50 m. to 9.00 m. | 15.43 | 219.2 | 3382.256 |
35 | Earth work for well excavation-Hard moorum lift from 9.00 m. to 9.50 m. | 14.96 | 227.9 | 3409.384 |
36 | Earth work for well excavation-Hard moorum lift from 9.50 m. to 10.00 m. | 14.62 | 236.6 | 3459.092 |
37 | Earth work for well excavation-Hard moorum lift from 10.00 m. to 10.50 m. | 14.31 | 245.3 | 3510.243 |
38 | Earth work for well excavation-Hard moorum lift from 11.00 m. to 11.50 m. | 13.75 | 267.1 | 3672.625 |
39 | Earth work for well excavation-Hard moorum lift from 11.50 m. to 12.00 m. | 13.45 | 278 | 3739.1 |
40 | Earth work for well excavation-Hard moorum lift from 12.00 m. to 12.50 m. | 13.15 | 288.9 | 3799.035 |
41 | Earth work for well excavation-Hard moorum lift from 13.00 m. to 13.50 m. | 12.61 | 310.7 | 3917.927 |
42 | Earth work for well excavation-Hard moorum lift from 13.50 m. to 14.00 m. | 12.33 | 321.6 | 3965.328 |