S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 9000 | 4.1 | 36900 |
2 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 247.5 | 87.6 | 21681 |
3 | Chain and compass survey.-Headworks/Other Works | 0 | 584 | 0 |
4 | Stacking without boxing.-Puddle earth, moorum, sand or kankar | 2220 | 10.5 | 23310 |
5 | Stacking without boxing.-Metal, single, stone chips or quarry spalls | 600 | 25.6 | 15360 |
6 | Transportation rates for Masonry stone. | 0 | 0 | 0 |
7 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 600 | 173.97 | 104382 |
8 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 3024.35 | 120.69 | 365008.8015 |
9 | Labour only for spreading, hand packing, and levelling to gradient and required camber as per MOST 2004 clause 404.3.3 of metal grading-2 & 3 as per MOST 2004 clause 400.2.5 including dressing. | 2220 | 41 | 91020 |
10 | Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia | 50 | 311.8 | 15590 |
11 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1282.35 | 24.9 | 31930.515 |
12 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 2987 | 27 | 80649 |
13 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 4516.85 | 97.7 | 441296.245 |
14 | Earth work in rough excavation,filling excavated earth into depressions on banking as directed ,top surface to be levelled and neatly dressed.-Loose or soft soil | 360 | 130.8 | 47088 |
15 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Hard moorum | 240 | 114.3 | 27432 |
16 | Surface dressing of ground, including removing vegetation, and/ or unequalities not exceeding 15cm deep and disposal of rubbish lead upto 20m And lift upto1.5m-Dense or hard soil. | 600 | 80.5 | 48300 |
17 | work charge | 101000 | 1 | 101000 |