S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 1500 | 1500 |
2 | Survey & Investigation | 1 | 16471 | 16471 |
3 | Setting out work Refferance pillers, refferancing bench mark and temporary bench mark Construction of Reference Bench Mark 50x50x70 cm. made of 1:3:6 cement concrete i/c excavation of 50x50x50 cm pit, working benchmark 30x30x45 cm at every 500 m interva | 1 | 10883 | 10883 |
4 | Site clearance, cutting grass, raking into heaps and removing off the premises | 10000 | 3 | 30000 |
5 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Dense or hard soil | 40.46 | 127.7 | 5166.742 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 6 | 1927.5 | 11565 |
7 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2.5:5 (1cement, 2.5 sand, 5metal) | 38.12 | 2282.7 | 87016.524 |
8 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size) | 2591.5 | 0.16 | 414.64 |
9 | False work for R.C.C. and P.C.C. work in plinth and foundation | 134.56 | 155.3 | 20897.168 |
10 | Providing and placing in position tested steel for R.C.C. work including cutting, bending, binding etc. as per drawings and placing in position complete up to floor two level including cost of binding wire and all wastage etc. complete.-Mild steel and Medium tensile steel bars | 20 | 51.7 | 1034 |
11 | Transportation of metal | 4288.03 | 99.27 | 425672.7381 |
12 | Transportation of metal | 325 | 139.59 | 45366.75 |
13 | Providing and filling in foundation trenches and at the back of abutments, wing walls etc. and below pipe bed in layers not exceeding 15cm thick including watering and compacting including all lead and lifts.-Selected granular material in filling. | 32.8 | 584.6 | 19174.88 |
14 | Providing and laying reinforced cement concrete pipes N.P.3 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-1000 mm dia. | 12 | 3853.2 | 46238.4 |
15 | Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making | 1350 | 18.4 | 24840 |
16 | Compaction of soil for construction of subgrade & earthen shoulders with approved transported material collected and stacked at site, i/c spreading, making 4% camber and required gradient by tractor mounted grader or labourers, watering at OMC and compact | 2576.51 | 24.7 | 63639.797 |
17 | Compaction of hard shoulder collected at site, i/c making 4-5% camber by tractor mounted grader or labourers, watering at OMC and compacting with 80 to 100 kN static weight rollers to achieve desired density minimum 100% of the MDD as per IS:2720 (Part-7) | 330 | 35.9 | 11847 |
18 | Construction of gravel base course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more to bring the material in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clau | 525 | 576.9 | 302872.5 |
19 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to clause 2.2.2.2, plasticity characteristics of fines as per clause 2.2.3 of IRC:SP: | 140 | 508.6 | 71204 |
20 | Lossening of hard soil by ploughing the existing gound | 4651.11 | 2.7 | 12557.997 |
21 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 4820.51 | 50 | 241025.5 |