S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Contingency | 1 | 11862 | 11862 |
3 | Work charge | 1 | 3670 | 3670 |
4 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 238.22 | 23.9 | 5693.458 |
5 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:2:4 (1cement, 2sand, 4graded stone aggregate 20 mm nominal size) | 20.47 | 3698.39 | 75706.0433 |
6 | False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift | 437.09 | 250.5 | 109491.045 |
7 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 791.43 | 56.2 | 44478.366 |
8 | TRANSPORTATION OF MATERIAL | 1 | 10000 | 10000 |
9 | Earth work for well excavation including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 436.98 | 238.22 | 104097.3756 |