S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 2000 | 1 | 2000 |
2 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 162.2 | 73.2 | 11873.04 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 43.4 | 2464 | 106937.6 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 43.4 | 1885.5 | 81830.7 |
5 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 43.4 | 39.8 | 1727.32 |
6 | False work for R.C.C. and P.C.C. work in plinth and foundation | 194.4 | 112.3 | 21831.12 |
7 | Labour Charges for Laying Hume Pipes | 0 | 0 | 0 |
8 | Add if Lead is more than 5.00Km-For every 0.5 Kms. Lead beyond 10 Kms. and part there of upto 30 Kms. | 162.2 | 208.62 | 33838.164 |
9 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 162.2 | 34 | 5514.8 |
10 | Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN | 162.2 | 22.7 | 3681.94 |
11 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work | 162.2 | 67.8 | 10997.16 |
12 | Collection of hard moorum including stacking at quarry. | 162.2 | 109.3 | 17728.46 |
13 | contingency | 2040 | 1 | 2040 |
14 | 0402 Filling foundation and around masonry work with moorum I/c ramming layers and watering.
| 0 | 0 | 0 |
15 | 0307 Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gett
(b) Dense or hard soil
| 0 | 0 | 0 |