S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 700 | 0.3 | 210 |
2 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 78.75 | 882 | 69457.5 |
3 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 12 mm graded metal is used | 39.38 | 3307.4 | 130245.412 |
4 | False work for R.C.C. and P.C.C. work in plinth and foundation | 70 | 147.8 | 10346 |
5 | Coursed rubble masonry second sort in plinth and foundation.-In Cement mortar 1:8 (1cement, 8sand) | 236.25 | 2082.1 | 491896.125 |
6 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing | 35 | 78.5 | 2747.5 |
7 | Transportation of metal | 78.75 | 136.7 | 10765.125 |
8 | Transportation of sand | 116.24 | 259.83 | 30202.6392 |
9 | Transportation rates for Masonry stone. | 236.25 | 211.25 | 49907.8125 |
10 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 23.63 | 123.03 | 2907.1989 |
11 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 21.09 | 112.32 | 2368.8288 |
12 | Transportation rates for Lime (fat), Hydraulic or any other. | 33.47 | 355.7 | 11905.279 |
13 | SIGN BOARD | 1 | 4000 | 4000 |
14 | Lossening of hard soil by ploughing the existing goundSpreading, dressing , breaking of clods of ploudged earth upto 20 m, lead and lift upto 1.5 mt, disposed soil to be leveled and neatly dressed | 393.75 | 52.7 | 20750.625 |
15 | contingency | 1 | 20989.9546 | 20989.9546 |