State: MADHYA PRADESH District: REWA Block: GANGEV Panchayat: TIKURI -32
Work Code: 1713004067/IF/9993728926 (Kapildhara koop Rajbahor Patel Ts 2441)
Work Category: Drought Proofing
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Perspective Plan :
Proposal Date : 26/1/2016 Work start date : 1/4/2016
Present status : Not Exist Proposed Status : Well
Tech Sanction Details
Technical Sanction No. : 4067/2441 Sanction Date : 18/2/2016
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
155000 275000 0 0 0 0 0 275000 0 430000
Financial Sanction Details
Financial\Administrative Sanction No: 2441/54 Financial\Administrative Sanction Date 24/2/2016
Fin. Sanc. Amt. (in Rs) NREGA:430000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
430000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard115001500
2Site clearance, cutting grass, raking into heaps and removing off the premises11.61.6
3Work charge11241912419
4Pumping out water caused by springs tidal or river seepage, broken water mains or drains or well point pumping and the like.60583480
5Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)23234.36468.6
6False work for lintels slabs, columns, walls, sills, chhajjas balconies, beams, stair cases or ornamental moulded work, curved surface etc. cast in situ including all lead and lift2.701182.9494.0129
7Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Lime Mortar 1: 2(1lime, 2sand)752595194625
8Add extra for brick masonry circular in plan, I/c wells to a mean radius not exceeding 6m (Such as well stening and other similar type of works)75237.917842.5
9Add to item no.0605 and 0609 for well staining-For every 3meter up to 15 meter depth.64.77378.6324523.8651
10Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing18278.514287
11Transportation of metal 1155.4155.4
12Earth work for well excavation including disposal or stacking of excavated soil lead upto 50m lift upto 1.5m-Hard rock requiring blasting.3686731212
13Add in item No. 2401 for lift. (In well excavation)-For every 0.50 m after 1.5 m initial depth upto 6.0 m55270.8914898.95
14Add in item No. 2402 for lift. (In well excavation)-For every 0.50 m after 1.5 m initial depth upto 6.0 m36.285831.4730169.88895
15Extra rates for quantities of work executed. In or under water or in foul condition (extra rate for the main item concerned is allowed on account of slow progress of works)43.45173.427535.099
16Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Loose or soft soil for Tank Work5581.24466
17Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work55167.589216.9
18Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal or stacking of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.5760934713
19Collection of quarried stone or rubble.66181.111952.6
20Labour difference in case of old SoR194209420
Total Activity 430000
S.NoMaterialQuantityUnit PriceTotal
120 M.M. METAL150005000
240 M.M. METAL150005000
3Cement14500045000
4Contagecny11300013000
5sand motor16000060000
6Stones1105000105000
7TRAINSPORT CHARGE14050040500
8साईनबोर्ड 115001500
Total Material 275000