S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 1500 | 1500 |
2 | Cutting down trees (exceeding 30cm girth, grubbing uproot, filling pits and levelling off ground, lopping branches, trimming, removing not exceeding 50meter & staking serviceable material and cleaning site.-Girth exceeding 30 cm and not exceeding 100 cm | 1 | 132000 | 132000 |
3 | Work charge | 1800 | 3.5 | 6300 |
4 | Boring holes 3.5m deep in ordinary soil (for cast in situ piles) and getting out the soil (under ramming if any shall be paid for separately) and disposal of the surplus excavated soil as directed within a lead of 50m for-Diameter of piles.-200 mm | 20 | 296.9 | 5938 |
5 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 56.45 | 3007.5 | 169773.375 |
6 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 23.54 | 2343.8 | 55173.052 |
7 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 2.45 | 226.8 | 555.66 |
8 | Class 25 open bhatta or pajawa burnt brick masonry in plinth and foundation.-Lime Mortar 1: 2(1lime, 2sand) | 52.65 | 2074.6 | 109227.69 |
9 | Deduct for kumbhar brick class 20 burnt pajawa in item no. 0603 and 0605 | 35.42 | 162.3 | 5748.666 |
10 | Providing and fixing 25mm thick single leaf battened and framed door shutter including bright finished or/and black enamelled M.S. butt hinges with necessary screws.-Bija wood | 200 | 705.8 | 141160 |
11 | Providing and fixing flush door shutters, solid core construction, decorative type with skins of decorative veneered particle boards and block board core, with frame of first class hard wood with particle board veneered particle board face panels includin-40 mm thick (double leaf) | 123.1 | 1587.9 | 195470.49 |
12 | 15mm thick cement plaster on rough side of wall in-Cement mortar 1:3 (1cement, 3sand) | 985.44 | 111.2 | 109580.928 |
13 | Extra for providing and fixing glass strips in joints of floors-40 mm wide 4 mm thick. | 1800 | 15.3 | 27540 |
14 | Transportation of metal | 635 | 114.1 | 72453.5 |
15 | Site clearance, cutting grass, raking into heaps and removing off the premises | 7200 | 1.6 | 11520 |
16 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed. | 1500 | 60.2 | 90300 |
17 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti | 265 | 414.5 | 109842.5 |
18 | 1902 Transportion of metal | 895 | 208.4 | 186518 |
19 | Labour difference in case of old SoR | 1200 | 14 | 16800 |