S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Cement Lime Mortar 1:1:8 ( 1 cement, 1 lime putty, 8 sand ) | 250 | 1858.7 | 464675 |
2 | Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering. | 70 | 882 | 61740 |
3 | Pointing on CR masonry with cement mortar 1:4(1cement, 4sand)-Flush pointing | 320 | 127.6 | 40832 |
4 | Collection of through/ bond stones. | 44 | 260.26 | 11451.44 |
5 | Transportation of 20 MM metal | 14 | 3307.7 | 46307.8 |
6 | Transportation of sand | 13.38 | 475.11 | 6356.9718 |
7 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 4.92 | 267.21 | 1314.6732 |
8 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 600 | 96.2 | 57720 |
9 | SIGN BOARD | 1 | 5000 | 5000 |
10 | contingency | 1 | 53710 | 53710 |