The Mahatma Gandhi National Rural Employment Guarantee Act 26-Sep-2024 10:12:35 AM 
Back  
State: MADHYA PRADESH District: KHANDWA Block: PANDHANA Panchayat: BADGAON PIPLOD
Work Code: 1725007005/RC/22012034187926 (पंच परमेश्‍वर सीसी रोड सह नाली निर्माण कार्य कैलाश)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 1/6/2013 Work start date : 20/6/2013
Present status : Earthern road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 59 bp Sanction Date : 3/7/2013
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Panchparmeshwar scheme2 scheme3 Total
93000 62000 0 0 291000 0 0 353000 0 446000
Financial Sanction Details
Financial\Administrative Sanction No: 01 bp Financial\Administrative Sanction Date 5/7/2013
Fin. Sanc. Amt. (in Rs) NREGA:155000 Panchparmeshwar
291000
Scheme 2
0
Scheme 3
0
Total
446000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil114.2481.29276.288
2Dag-beling-Double spade "v" shaped stroke 100mm deep4800.5240
3Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)99.553177.8316349.99
4Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used99.55118.611806.63
5False work for R.C.C. and P.C.C. work in plinth and foundation144154.222204.8
6Providing and filling in position blown bitumen in expansion joints (10cm deep and 1cm Wide)1606.31008
7Collection of approved soil having CBR not less then 12, including stacking at quarry.102.82118.812215.016
8Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 102.827.5771.15
9Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 97.6403904
10Transportation of metal 84.62214.518150.99
11Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.167.53140.6323559.7439
12Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7102.8223.62426.552
13work charge12408624086
Total Activity 446000
S.NoMaterialQuantityUnit PriceTotal
120 MM B.T.METAL100084.6284620
2Cement000
3CEMENT(BEGS)610300183000
4Centering and Shuttering144608640
5Display board125002500
6Gunny BAG50052500
7mason perday143004200
8mixer machin (perday)1480011200
9PhotoCopy & Stationary1102220
10Photograph1025250
11Plastic48031440
12SAND42.8180034248
13TANKER NO64002400
14Thermocoal5100500
15Transportanion of hard Muram102.8210010282
16Vibrator (Per Day)145007000
Total Material 353000