S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 9000 | 4.1 | 36900 |
2 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 486 | 87.6 | 42573.6 |
3 | Collection of approved soil having CBR not less than 5, including stacking at quarry. | 360 | 130.8 | 47088 |
4 | Collection of approved soil having CBR not less then 12, including stacking at quarry. | 240 | 114.3 | 27432 |
5 | Stacking without boxing.-Puddle earth, moorum, sand or kankar | 2222 | 14.58 | 32396.76 |
6 | Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars. | 1734 | 139.12 | 241234.08 |
7 | Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7 | 2220 | 51.67 | 114707.4 |
8 | Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia | 37.5 | 311.8 | 11692.5 |
9 | Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor | 1957 | 27 | 52839 |
10 | Construction of gravel surface course by naturally occurred gravel or river born material or by crushed metal or mixture of two or more in appropriate grading confirming to Table 2.2 of IRC:SP:77-2008, having Liquid Limit less than 25 and Plasticity inde | 600 | 61.5 | 36900 |
11 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed - Dense or hard soil for Well Work | 3228.82 | 81.2 | 262180.184 |
12 | work charge | 1 | 45000 | 45000 |
13 | Fixing of Information board with diging pits and grout in cement concret mixture (1:2:4). Mandays per board | 1 | 5933 | 5933 |