State: MADHYA PRADESH District: GWALIOR Block: BHITARWAR Panchayat: SIRSULA(P)
Work Code: 1703004079/FP/22012034632368 (Flood Cantrol wall Nirman Poorvav Flood kantrol wal se shanti dham ki or bhadeshwar)
Work Category: Other Works
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2022-2023 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : NO Perspective Plan : NO
Proposal Date : 24/1/2023 Work start date : 1/2/2023
Present status : Weak Embankment Proposed Status : Constr of drain for coastal protection for Comm.
Tech Sanction Details
Technical Sanction No. : 4079/3176 Sanction Date : 25/1/2023
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost 14th Fianance Commission scheme2 scheme3 Total
790000 520000 0 0 187000 0 0 707000 0 1497000
Financial Sanction Details
Financial\Administrative Sanction No: AS079/22 Financial\Administrative Sanction Date 30/1/2023
Fin. Sanc. Amt. (in Rs) NREGA:1310000 14th Fianance Commission
187000
Scheme 2
0
Scheme 3
0
Total
1497000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.4807.043379.2
2Excavation in trenches for foundations and for pipes, cables, etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms, lift upto 1.5m including getting out and-Hard rock requiring blasting288156.7945155.52
3Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m1200114.56137472
4Filling foundation or under floor with 40mm gauge graded metal and moorum including ramming in layers and watering.483202.91153739.68
5Add to item No. 0413 and 0415 if in place of 40mm metal.-If 12 mm graded metal is used50.63947.45199740.97
6False work for R.C.C. and P.C.C. work in plinth and foundation34174.25922.8
7Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:8 (1cement, 8sand)2922732.88798000.96
8Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Flush pointing70171.3511994.5
9Transportation of metal 46.52234.0410887.5408
10Transportation rates for Masonry stone.194.4506.2498413.056
11Transportation rates for Moorum, sand, earth, surkhi, fly ash, cement and mortars.140.226226.3831744.36188
12Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Hard moorum000
Total Activity 1497000
S.NoMaterialQuantityUnit PriceTotal
120 MM METAL38.4125048000
240 mm Metal59.4173.2710292.238
3BOLDER DHULAI BAHADA SAHIT267.3411.77110066.121
4Cement615390239850
5Centring & Shuttering000
6Display board150005000
7Sand1781650293700
Total Material 707000