S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Loose or soft soil | 490.7 | 245.35 | 120393.245 |
2 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 4059.66 | 136.31 | 553372.2546 |
3 | Earth work in excavation in trenches for foundations and for pipes, cables etc. not exceeding 1.5m in width and for shafts, cesspits and the like not exceeding 10sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including getti-Loose or soft soil | 32.4 | 148.33 | 4805.892 |
4 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 53.4 | 3823.54 | 204177.036 |
5 | 22cm thick dry stone picked up boulder pitching i/c picking of boulder with individual size of 22cm depth. | 327 | 207.47 | 67842.69 |
6 | Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for | 1458 | 2.39 | 3484.62 |
7 | Transportation of metal | 71.94 | 169.7 | 12208.218 |
8 | Transportation of metal | 162 | 189.6 | 30715.2 |