S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 680 | 0.3 | 204 |
2 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal) | 37.4 | 3307.4 | 123696.76 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal) | 51 | 2202.3 | 112317.3 |
4 | Steel work welded in built up sections, framed work, including cutting hoisting fixing in position in gratings, frames, guard bars, ladders, railing, brackets and similar works & trusses and trussed purlins up to 25m span and 15 m over all height | 150 | 59.1 | 8865 |
5 | Pointing on random rubble masonry or uncoursed stone masonry with cement mortar 1:4 (1cement, 4sand)-Raised and cut pointing | 1020 | 127.6 | 130152 |
6 | Demolition above G.L. upto floor two level including disposal of unserviceable materials within 100 metres lead.-Lime concrete. | 163.2 | 2220.3 | 362352.96 |
7 | Demolition above G.L. upto floor two level including disposal of unserviceable materials within 100 metres lead.-Unreinforced cement concrete more then 15 cm thickness. | 244.8 | 1858.7 | 455009.76 |
8 | Transportation of metal | 46.92 | 218.7 | 10261.404 |
9 | Transportation of 20 MM metal | 31.79 | 288.7 | 9177.773 |
10 | Transportation of sand | 214.78 | 320.13 | 68757.5214 |
11 | Transportation rates for Boulders, Laterite, rubble pitching stones and excavated hard rock. | 408 | 453.18 | 184897.44 |
12 | Loading & stacking of cement from the-Deptt. godown or site to truck, dumper etc. | 36.19 | 89.91 | 3253.8429 |
13 | Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil | 229.5 | 52.7 | 12094.65 |
14 | contingency | 1 | 14000 | 14000 |