State: MADHYA PRADESH District: DAMOH Block: BATIYAGARH Panchayat: TINDUWA
Work Code: 1711003045/RC/22012034289041 (Nali nirman Sukai ke ghar se nale ki or)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2015-2016 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 15/8/2015 Work start date : 13/11/2015
Present status : No Road Proposed Status : Cement Concrete
Tech Sanction Details
Technical Sanction No. : 229/tin Sanction Date : 30/10/2015
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
387000 258000 0 0 0 0 0 258000 0 645000
Financial Sanction Details
Financial\Administrative Sanction No: 01/tn Financial\Administrative Sanction Date 1/11/2015
Fin. Sanc. Amt. (in Rs) NREGA:645000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
645000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard120002000
2Site clearance, cutting grass, raking into heaps and removing off the premises3861.6617.6
3Contingency11261112611
4Work charge13148431484
5Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering lead upto 50m and lift upto 1.5m69.4835.82487.384
6Filling foundation and around masonry work with moorum I/c ramming layers and watering.77.255.24261.44
7Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:2:4 (1cement, 2sand, 4metal)8.693089.926851.231
8Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:4:8 (1cement, 4sand, 8metal)77.21636.3126322.36
9Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used8.69169.41472.086
10Extra rate for laying cement concrete in or under water or liquid mud including cost of pumping and bailing out and removing slush etc. complete.77.278.16029.32
11Random / uncoursed rubble masonry in plinth and foundation including levelling up with cement concrete 1:6:12 (1cement, 6coarse sand, 12 aggregate 20mm nominal size) at plinth level.-In Cement mortar 1:8 (1cement, 8sand)156.331318.48206117.9784
12TRANSPORTATION OF MATERIAL16853068530
13Collection of approved soil having CBR not less than 5, including stacking at quarry.77.290.26963.44
14Collection of rubble masonry (size 0.014cum to 0.06cum) other then black trap, basalt or granite.156.33467.773115.541
15Collection of sand including screening, washing, stacking and all leads and lifts up to the loading point.50.19139.16981.429
16Earth work in excavation in trenches for foundations and for pipes,cables etc.not exceeding 1.5 m in width and for shafts,cesspits and the like not exceeding 10 sqm on plan including dressing of sides and ramming of bottoms lift upto 1.5m including gettin-Dense or hard soil424.688.337492.18
17Collection of hard metal other then black trap basalt and granite for road works (without blasting) including stacking as per MOST 1995, clause 400.2.5-Grading-3 (Size ranging from 53 mm to 22.4 mm)69.48455.731662.036
Total Activity 645000
S.NoMaterialQuantityUnit PriceTotal
140 mm Metal77.7519815394.5
2CEMENT(BEGS)503250125750
3contengency120002000
4First Aid Box1200200
5PhotoCopy & Stationary110001000
6SAND91.1960054714
7singboard120002000
8Transportation of Masonry Ston167.6720033534
9TRANSPORTATION OF MOORUM79.2138.4210962.864
10गिटटी 20 mm10.37120012444
Total Material 258000