Work Code: 1711003017/RC/22012034200902 (Construction of Gravel Road)
Work Category: Rural Connectivity
Note:
Total Material cost and Total Activity cost shown absolute value which is multiples of 100/1000!
Financial Year : 2013-2014 Execution Level : GP
Execution Agency : Gram Panchayat(3) Work Status : Approve
Included in Annual Plan : Yes Perspective Plan : Yes
Proposal Date : 2/10/2013 Work start date : 20/1/2014
Present status : No Road Proposed Status : Gravel Road
Tech Sanction Details
Technical Sanction No. : 1278/Mangola Sanction Date : 15/1/2014
Estimated Cost as per Tech. Detl (in Rs.)
Unskilled Material Contingency Total
Est. Material Cost Est. Skilled Cost Est. Semi-Skilled Cost Scheme1 scheme2 scheme3 Total
678391 479609 0 0 0 0 0 480000 0 1158000
Financial Sanction Details
Financial\Administrative Sanction No: 20/Mangola Financial\Administrative Sanction Date 16/1/2014
Fin. Sanc. Amt. (in Rs) NREGA:1158000 Scheme 1
0
Scheme 2
0
Scheme 3
0
Total
1158000
S.NoActivity taken upon musterollQuantityUnit PriceTotal
1signboard15933.75933.7
2Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared.47254.119372.5
3Contingency15218852188
4Chain and compass survey.-Canals/Roads0.7584408.8
5Theodolite work involving fixing of stones at every tenth chain, tangent, apex and vertex points final alignment.0.77462.95224.03
6Fly levelling for fixing temporary bench marks.-Above 15 m interval0.7438306.6
7Levelling - Headwork.-Below 5 m interval0.714601022
8Levelling - Headwork.-Above 15 m interval0.7467.2327.04
9Transportation charges of water for every additional 200m or part thereof, beyond initial lead of 200m up to 2 Km. Lead for 4371626226
10Transportation of metal 2343138.42324318.06
11Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock.168197.633196.8
12Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing.2090.94185726.9
13Labour only for spreading, hand packing, and levelling to gradient and required camber as per MOST 2004 clause 404.3.3 of metal, grade-1 As per MOST 2004 clause 400.2.5 including dressing.42080.533810
14Rolling & Compaction of granular sub-base of well graded material, spreading in uniform layers with tractor mounted grader on prepared surface, mixing by mix in place, sprinkling of water till OMC, and compacting with smooth wheel rollers of 80 to 100 kN42061.525830
15Providing and laying reinforced cement concrete pipes N.P.2 for culverts including pointing ends, and fixing collar with cement martar 1:2 complete.-300mm dia40312.912516
16Compaction of embankment with approved materials as per clause 301.4 & 301.5 of specifications for rural roads(MORD), already spreaded at site, obtained from roadway cutting, excavated from drains, foundation of other structures or from borrow pit, making1860.222.642040.52
17Compaction of soil for construction of subgrade & earthen shoulders with approved material, already spreaded at site, obtained from roadway cutting, drains, foundation of other structures or barrow pits, i/c making 4% camber and required grade by tractor2090.92450181.6
18Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 20m and lift upto 1.5m, disposed soil to be levelled and neatly dressed -Dense or hard soil for Road Work1860.281.2151048.24
19Collection of soft moorum including stacking at quarry.2090.9112.8235853.52
20Collection of hard moorum including stacking at quarry.420122.5551471
Total Activity 1158000
S.NoMaterialQuantityUnit PriceTotal
1BGSY SIGN BOARD159345934
2Compaction of Earth Work1860.1822.642040.068
3Compaction of GSB42061.525830
4Compaction of Selected soil2090.92450181.6
5contangency and work charges13339333393
6hume pipe40312.912516
7Kilometre Stone (200 M)53341670
8Kilometre Stone (ordinary)26871374
9km stone143304620
10setting out work162566256
11Transportation of GSB168157.6826490.24
12Transportation Of Selected Soi2342.999231947.1
13upkar 111113111131
14watering4371626226
Total Material 480000