S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | signboard | 1 | 2000 | 2000 |
2 | Site clearance, cutting grass, raking into heaps and removing off the premises | 1 | 985 | 985 |
3 | Contingency | 1 | 100000 | 100000 |
4 | Work charge | 1 | 73000 | 73000 |
5 | Earth work in bulk excavation (exceeding 30cm in depth, 1.5m in width as well as 10sqm on plan) including disposal of excavated soil lead upto 50m and lift upto 1.5m, disposed soil to be levelled and neatly dressed.-Dense or hard soil | 316.9 | 65 | 20598.5 |
6 | Providing and fixing barbed wire fencing with 5 rows of horizontal barbed wire and 2 digonal rows tightened to RCC post as per IS:4996-1984, 1.85M long, 1.25 m above and 0.6 m belowe ground level, c/c spacing of each post shall not exceed 3M with diagonal | 130 | 80.22 | 10428.6 |
7 | TRANSPORTATION OF MATERIAL | 1 | 13000 | 13000 |
8 | Supply of vermi compost | 7970.4 | 5 | 39852 |