S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 0.5 | 600 | 300 |
2 | Extra for every additional Lead beyond 50metres or part thereof upto 200 m for every 50 m lead | 200 | 94.4 | 18880 |
3 | Providing and laying in foundation, plinth and under floors cement concrete with 40mm nominal size graded stone aggregates (metal) i/c ramming in layers and curing complete excluding cost of form work-C.C. 1:3:6 (1cement, 3sand, 6metal) | 2592.6 | 50 | 129630 |
4 | Add to item No. 0413 and 0415 if in place of 40mm metal.-If 20 mm graded metal is used | 62 | 3564.1 | 220974.2 |
5 | Providing and placing in position RCC for roof, beams, columns column footing lintels chhajjas, balcony, stairs etc, excluding cost of reinforcement & centring but including finishing & curing.-CC 1:1:2 (1cement, 1sand, 2graded stone aggregate 20 mm nominal size) | 2 | 619 | 1238 |
6 | Labour only for moorum, screening or binding material as per MOST 2004 clause 400.2.6 spreading on boulder or WBM coat as per MOST 2004 clause 404.2.7 | 300 | 44.1 | 13230 |