S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Dag-beling-Single spade stroke minimum 75mm deep | 200 | 0.2 | 40 |
2 | Providing and fixing in cement mortar 1:6 (1cement, 6sand) flag stone slab over drains.-30 mm thick | 218.6 | 140 | 30604 |
3 | Hammer dressed 15cm thick stone paving laid in camber in moorum bedding and filled with moorum mortar. | 215.7 | 300 | 64710 |
4 | Transportation rates for Bricks, kanker, stone chips shingle & excavated materials in disintegrated rock & soft rock. | 132.84 | 69.92 | 9288.1728 |
5 | Loading of metal in truck, dumper etc. | 26.28 | 69.92 | 1837.4976 |
6 | Unloading of metal in truck, dumper etc. | 13.14 | 69.92 | 918.7488 |
7 | Labour only for moorum, kankar, shingle/ gravel/red bajri spreading levelling to gradient and required camber including dressing. | 41 | 69.92 | 2866.72 |
8 | Collection of hard moorum including stacking at quarry. | 130.8 | 69.92 | 9145.536 |
9 | Preparation of sub grade by excavating earth work to the 15cm average depth, dressing to camber including making good the undulations etc. and disposal of surplus earth with lead upto 20metres and upto 1.5metre.-Loose or soft soil. | 1 | 21374 | 21374 |