S.No | Activity taken upon musteroll | Quantity | Unit Price | Total |
1 | Jungle clearance including uprooting of rank vegetation, grass, brush wood, saplings and tree not exceeding 30cm girth and removing not exceeding 50meters outside the periphery of the area cleared. | 1912.5 | 6.64523921568628 | 12709.02 |
2 | Providing stone chips under stone pitching | 360 | 454.87925 | 163756.53 |
3 | (a) Other then black trap Basalt or granite | 131.4 | 301.756925418569 | 39650.86 |
4 | (a) Consolidation of Moorum /earth work (rate for 1Cum. of Moorum /earth work) | 3095.1 | 2.38837517366159 | 7392.26 |
5 | (XI) 6 Km. Lead | 131.4 | 262.241400304414 | 34458.52 |
6 | (III) 1.5 Km. Lead | 1023.75 | 77.9294358974359 | 79780.26 |
7 | (XII) 7 Km. Lead | 1901.25 | 179.096415516108 | 340507.06 |
8 | (XV) 10 Km. Lead | 170.1 | 210.634332745444 | 35828.9 |
9 | (a) Boulders | 126 | 576.088095238095 | 72587.1 |
10 | For earthen dam - puddle filling of good clay including lead upto 20 meter including mixing, watering & kneading by tamping , ramming & laying etc. | 170.1 | 428.469253380364 | 72882.62 |
11 | Hearting, casing/cut off filling soil etc.
At optimum moisture content to achieve maximum dry density by mechanical sheep foot roller/ vibratory compacters including watering, required leads and lifts and material etc. complete. | 3095.1 | 21.7850764111014 | 67426.99 |
12 | a (iii) Loose or soft soil for Tank Work | 79.99 | 100.973246655832 | 8076.85 |
13 | b (iii) Dense or hard soil for Tank Work | 1023.75 | 136.306246642247 | 139543.52 |
14 | c (iii) Hard moorum for Tank Work | 2003.85 | 181.559927140255 | 363818.86 |
15 | a (i) Disintegrated or soft rock (not requiring blasting) for Tank Work | 104.96 | 577.436356707317 | 60607.72 |